mmPERTT, Expected Duration of an Activity

Category: Project Management

The PERT Project Management function mmPERTT assumes that the time required to perform the project activities is not known with certainty. Using estimate duration this formula estimates the project completion time.

Business analysis formulas for Excel. Marketing tool for professionals

Where:

O = Optimistic estimate of the activity duration
ML = Most likely estimate of the activity duration
P = Pessimistic estimate of the activity duration

Syntax

mmPERTT(Optimistic, Most_Likely, Pessimistic)

Optimistic The smallest time estimate to complete the project
Most_Likely The most likely time estimate to complete the project
Pessimistic The largest time estimate to complete the project

Example

See example file Business Formulas.xls, sheet mmPERTT.

Business analysis formulas for Excel. Marketing tool for professionals

Related functions
  • mmDHMS
  • mmLEARN
  • mmPERTSD
  • mmPERTVAR
  • mmINTERPOLE
  • mmMD1
  • mmMG1
  • mmMMS
  • mmMMSP
  • mmMMSQ
  • mmRANGE
  • mmRANK
Related MM4XL software tools
  • Quality Analyst
  • Decision Tree
  • Descriptive Statistics
  • Semantic Differential
  • Smart Map
Source
Cliff T. Ragsdale, 2001, Spreadsheet modeling and decision analysis
Lifetime license:

Price: euro

Vote this tool
We proudly serve
Your vote
vote1 vote2 vote3 vote4 vote5
Email:
Gender:
M
F
Age:
Position:
Department:
Comment: